This project involved a study and build out of the inter-connection of the chilled water plants in the Anderson Student Center, Anderson Recreation Center, and the Murray-Herrick Center at the University of St. Thomas (UST).

The MCE team used PipeFlo software to assess the feasibility of interconnecting three separate chilled water plants into one central plant. After the assessment, we designed the interconnection piping, plant modifications, and sequence of operation updates to enable the plants to work together.

This enabled the northern half of the University of St Thomas campus to use one chiller instead of three chillers during low loads and significantly reduced energy consumption.

Explore other projects

Allianz building

Allianz | Corporate Headquarters

Engineered for future flexibility.

Avivo’s building and parking lot

Avivo | Headquarters

A building designed to help people and the planet.

Exterior of building

Baker Center

Utilizing lighting design to create an aesthetically beautiful space.

Office space with working spot

Boston Consulting Group

Cultivating an “up north” feel in the heart of Minneapolis.

City Center exterior building

City Center

Mixed-use tower at the heart of Minneapolis.

Code 42

Combining world-class design with incredible sustainability initiatives.


Connect with us to discuss your next project

We are always ready to jump in on a complicated and challenging project or simply to connect and expand our networks.

MCE building