Facts & Stats
Client
University of St. Thomas
Market Type
Higher Education
Square Footage
3,200,000 SF
Location
St. Paul, Minnesota
Completion Date
January 2022
MCE completed a study and system redesign to interconnect chilled water plants serving multiple University of St. Thomas campus buildings, enabling them to operate as a single central plant. The project improved energy efficiency by allowing one chiller to serve campus cooling demands during low-load conditions, significantly reducing energy consumption.
Location
St. Paul, minnesota
This project involved a study and build out of the inter-connection of the chilled water plants in the Anderson Student Center, Anderson Recreation Center, and the Murray-Herrick Center at the University of St. Thomas (UST).
The MCE team used PipeFlo software to assess the feasibility of interconnecting three separate chilled water plants into one central plant. After the assessment, we designed the interconnection piping, plant modifications, and sequence of operation updates to enable the plants to work together.
This enabled the northern half of the University of St Thomas campus to use one chiller instead of three chillers during low loads and significantly reduced energy consumption.