Facts & Stats
Client
Metropolitan Airports Commission
Market Type
Aviation
Location
MSP Int’l Airport, Minneapolis, Minnesota
Completion Date
Ongoing
MCE led the phased replacement of the Metropolitan Airports Commission’s aging chiller plant, increasing cooling capacity by 25% while improving energy efficiency, reliability, and operational flexibility. The modernization supports the growing needs of Minneapolis-St. Paul International Airport and includes system upgrades that reduced pumping energy by 60% and enhanced plant performance across a wide range of cooling loads.
Location
minneapolis, Minnesota
MCE replaced the Metropolitan Airports Commission (MAC) aging chiller plant in three phases of construction. The result of that construction was a 25% increase in cooling capacity, a similar increase in energy efficiency, and significant improvements in plant reliability and versatility.
By the completion of Phase 1, new construction in the terminal had increased the loads to almost 8,000 tons, but the plant was doing a better job of keeping up. Increased pumping capacity and the addition of two more chillers in Phase 2 boosted plant capacity to 9,000 tons and restored the plant’s original 2,000-ton backup system. It also enabled the plant to carry loads as small as 100 tons with operating efficiencies far better than the plant’s full-load efficiency. Phase 3 reduced pumping energy by 60% and drove the peak load back down to just over 7,000 tons.