Confidential Project C

Built in phases, this Tier 3 designed project includes a quad redundant electrical system supported by four generators with separate utility feeds. The quad redundancy supports continuous cooling and stays quad redundant down to the cabinet level to provide the building with flexibility and limits the stranded power.  IT floor design is averaged at 300

Confidential Project D

This large financial data center was fully designed and never built due to company mergers. The building consisted of two data room floors of almost 40,000 square feet each.  The mechanical and electrical systems are designed to Tier 4 redundancy.  Electrically, a tri-redundant system is supported by seven 2.5 MW generators with an ultimate build